LCLS-II Procurement
LCLS-II Procurement Team Leads
ANL POC:
Joe Ingraffia,
jingraffia@anl.gov,
630-252-7028
[ ANL Procurement Public Site ]
------------------
FERMI POC:
Jerry King,
jking@fnal.gov,
630-840-5551
Terry Cross,
tcross@fnal.gov,
630-840-3763
[ FNAL Procurement Public Site ]
------------------
TJNAF POC:
Mitch Laney,
laney@jlab.org,
757-269-5338
[ JLAB Procurement Public Site ]
------------------
LBNL POC:
Laura Crosby,
lbcrosby@lbl.gov,
510-495-2607
[ LBNL Procurement Public Site ]
------------------
SLAC POC:
Howard J. Wilson Jr.,
hwilson@slac.stanford.edu,
650-926-2769
[ SLAC Procurement Public Site ]
Description | SOL Date, Award Timeframe |
---|---|
SLAC | |
Cable Plant Installation Phase 2 | FY 17 Q1, FY 17 Q2 |
Conduit and Penetration Bundle installation | FY 17 Q2, FY 17 Q3 |
KB Mirror Chamber | FY 17 Q3, FY 17 Q4 |
Cable Plant Installation Phase 3 | FY 18 Q2, FY 18 Q3 |
NEH Renovation | FY 18 Q1, FY 18 Q2 |
FERMI | |
1.3 GHz Beamline Interconnect Parts | FY 17 Q1, FY 17 Q2 |
3.9 Fundamental Power Couplers | FY 17 Q2, FY 17 Q3 |
3.9 Cavities ( DRESSED) | F7 17 Q3, FY 17Q3 |
TJNAF | |
Gas Purification Compressor | FY 17 Q1, FY 17 Q2 |
HOM Absorbers | FY 17 Q1, FY 17 Q2 |
Fabricate Cryo Controls | FY 17 Q1, FY 17 Q2 |
Fabricate Transfer Lines | FY 17 Q1, FY 17 Q2 |
Instrument Air Systems | FY 17 Q1, FY 17 Q1 |
2 K Cold Box | FY 17 Q2, FY 17 Q3 |
Warm He Gas Storage Tanks | FY 17 Q1, FY 17 Q1 |
Gas Management System | FY 17 Q1, FY 17 Q2 |
Lhe Storage Dewar | FY 17 Q1, FY 17 Q1 |