LCLS-II-HE Checkout & Commissioning Dashboard
Checkout & Dashboard
| Injector Restart | SC Linac Restart? | L4 SRF (pre-beam) | Beam to BSYD | Spreader/LTU/ Undulator | Post-TTO Commissioning |
|---|---|---|---|---|---|
| Scope | Scope | Scope | Scope | Scope | beam_power_stages |
| prebeam Checks | Prebeam Checks | Precooldown and Prebeam Checks | Prebeam Checks | Prebeam checkout
| |
Plans/Sheets
| Plans/Sheets
| Plans/Sheets
| Plans/Sheets
| Plans/Sheets
| Plans/Sheets
|
| Additional docs | Additional docs | SRF_relevant | Additional docs | Additional docs | LCLS physics meeting (Thu 9am) |
| Common files | Machine diagram layout PDF file HLA GUI task assignment timetable HLA GUI documents; HLA programmer guide; HLA sharepoint Other supporting documents; Some archived links
| ||||