Physicist Axel Brachmann with a vacuum transport chamber. August 26, 2008
The injector for the Linac Coherent Light Source has a shiny new electron source, or cathode, thanks to a recent repair project aimed at correcting a problem that began earlier this summer. more...
August 26, 2008
Congratulations to the scientists and engineers of the Linac Coherent Light Source Ultrafast Science Instrumentation project, or LUSI. The team last week successfully completed Department of Energy review for Critical Decision 2, or CD2. more...
August 19, 2008
The balance of activity on the Linac Coherent Light Source project has shifted from building infrastructure to installing hardware, with all but the final construction "punch-list" items completed. The tunnels, utilities, fire suppression systems, cooling water and electrical systems are nearly ready for prime time. more...
August 07, 2008
LCLS hereby invites the world’s research community to submit scientific proposals for experiments with soft X-rays at the AMO experimental station. Proposals for the first LCLS operation period (July-December 2009) must be submitted by September 1, 2008. more...
August 01, 2008
Construction highlights from the Linac Coherent Light Source (LCLS) this month include... more...
July 25, 2008
Construction of the Linac Coherent Lights Source (LCLS) continues at a rapid pace. Since the completion of tunneling earlier this year, crews have finished out the Far Experimental Hall and X-ray Tunnel, installed utility systems in the Central Utilities Plant and throughout the facility, and are approaching completion of the Near Experimental Hall (NEH). more...
July 08, 2008
Flash imaging of nanoscale objects undergoing ultrafast changes is now a technical possibility, according to a recent paper published in the June 22 edition of Nature Photonics. The results are a direct precursor to research that will be conducted using SLAC’s Linac Coherent Light Source (LCLS). more...
June 27, 2008
Construction highlights for the Linac Coherent Light Source (LCLS) for June, 2008 include...
more...
June 24, 2008
This month SLAC welcomes Jochen Schneider, the most recent addition to the Linac Coherent Light Source (LCLS) team. Schneider initially came to SLAC last January as a visiting professor. His appointment as new director of the Experimental Facilities Division for the LCLS marks a big step toward making the LCLS a scientific reality. more...
June 03, 2008
This week, more than 50 prospective Linac Coherent Light Source (LCLS) users arrived at SLAC for a workshop focusing on the Atomic, Molecular and Optical (AMO) science instrument. more...
May 30, 2008
What do you get when you combine 120 concrete trucks filled with more than 1,000 cubic yards of concrete, with 350,000 pounds of steel rebar? "Happy physicists," according to Linac Coherent Light Source (LCLS) Conventional Facilities Manager David Saenz. more...
May 29, 2008
When particle accelerators gave birth to the powerful X-ray microscopes known as synchrotrons, they revolutionized the study of virtually every field of science. Now the Linac Coherent Light Source promises to make an equally big leap, making movies of atoms and molecules in action and changing the way we think about matter. more...
May 23, 2008
Construction highlights from the Linac Coherent Light Source for May, 2008 include... more...
May 16, 2008
The Office of Science semi-annually conducts reviews of its large major projects and this week it focused on the Linac Coherent Light Source (LCLS). Dan Lehman, the Director of the Office of Project Assessment in the Office of Science, leads this process and he arrived at SLAC with a large team of world-class scientists, engineers and management consultants to look over all aspects of the LCLS project. more...
May 12, 2008
Installation of the first undulator pedestals for the Linac Coherent Light Source (LCLS) is set to begin this week in the Undulator Hall. The final shipment of the stands arrived at SLAC last April from Argonne National Laboratory, where they were designed.
more...
April 21, 2008
In preparation for the upcoming call for proposals to use the LCLS for XPP experiments, a workshop will be held at SLAC June 20-21, 2008 to inform future XPP users of the status of the LCLS and assist them with preparing their proposals for beam time. more...
April 11, 2008
In preparation for the upcoming call for proposals to use the LCLS for AMO experiments, a workshop will be held at SLAC June 2-3, 2008 to inform future AMO users of the status of the LCLS and assist them with preparing their proposals for beam time. more...
March 14, 2008
The AMO end-station is in the final design process, with detailed drawings of the mechanical components being produced, commercial components specified and controls and data acquisition software being designed. This process is expected to last until the summer when a review of the design will be held and procurement of components begin. more...
February 07, 2008
Last week, trucks arrived with the first shipment of specially designed stands for Linac Coherent Light Source (LCLS) magnets and diagnostics to be installed in the Beam Transport Hall. This section of the LCLS, called the "linac-to-undulator," will connect the end of the linac to the undulator magnet arrays. more...
January 30, 2008
The tunneling breakthrough into the Far Experimental Hall (FEH) of the Linac Coherent Light Source (LCLS) on January 14th was the culmination of months of planning and excavation work. Having begun nearly a year ago, the FEH cavern is nearly complete, with only the pouring of the concrete slab floor remaining. Once the floor is poured, construction of the experimental hutches can begin. more...
January 22, 2008
Last week, undulator work in SLAC's Magnetic Measurement Facility (MMF) for the Linac Coherent Light Source (LCLS) entered a new chapter as workers for the first time mated an undulator with the girder to which it will eventually be mounted in the Undulator Hall (UH). more...
January 18, 2008
When the Linac Coherent Light Source (LCLS) was first conceived in 1992, an x-ray free-electron laser was considered an expensive and technically high-risk endeavor to create a light source with unprecedented and indeed uncertain potential. Early SLAC reports describing the LCLS concept hint at its scientific potential, but not much more. more...
January 15, 2008
Yesterday morning a crowd of about 60 onlookers, bedecked in hard-hats and reflective vests, witnessed the final tunneling break through for construction of the Linac Coherent Light Source (LCLS) in the dimly lit cavern of the Far Experimental Hall (FEH). more...
December 12, 2007
While most of SLAC sleeps, a select group remains hard at work, driving ahead construction progress on the Linac Coherent Light Source (LCLS). Since last spring, tunnel contractor Affholder Inc. has used double shifts to speed ahead tunneling progress, with the second shift on the clock from 4:00 p.m. to 2:00 a.m. more...
December 06, 2007
Menlo Park, CA—Persis S. Drell has been named director of the Stanford Linear Accelerator Center (SLAC), effective immediately, Stanford University President John Hennessy announced Thursday. Drell, a professor of physics at SLAC, has held a series of sen more...
November 21, 2007
How do you take a picture of something as thin as a strand of hair that's moving at the speed of light? more...
November 12, 2007
Construction crews working on the Linac Coherent Light Source (LCLS) site are busier than ever these days. Last week, the Beam Transport Hall, which bisects the research yard, began receiving the final yards of concrete for the roof after being connected to the Undulator Hall. more...
November 06, 2007
As construction continues on the experimental halls that will receive the beam from the Linac Coherent Light Source (LCLS), the instruments that will go inside still exist only in the minds and computers of the designers. But in the past few months, those instruments are getting closer to reality. more...
October 23, 2007
The Linac Coherent Light Source (LCLS) project is a collaboration that brings together components and equipment from dozens of suppliers. Last month, Craigslist.org joined that supply chain. more...
October 18, 2007
Last week, a team working with the Linac Coherent Light Source (LCLS) construction project repositioned dozens of undulator magnets to make room for pre-assembly of the undulator support pedestals. For months, the undulators have remained stored in wooden crates in the Collider Hall, and now the first stages leading to their installation next year are set to begin. more...
October 05, 2007
Pief Panofsky built a laboratory with a single purpose: to probe the fundamental structure of matter with the world’s largest electron accelerator. During his lifetime, the lab reinvented itself many times in order to stay on the frontiers of scientific discovery. more...
|